On a mission to habituate Nayaraipur….citizens' initiative
project-completion

Progress status

1. NRDA has constructed 75 KM of 4 lane / 6 lane city level road network and additional 60 KM of roadwork is under construction.
2. City level underground electrical infrastructure with 10 nos. of 33 KVA Sub-station (Indoor) is in place. The said system is SCADA complaint.
3. City level Water Supply has been commissioned
4. Sewerage network & construction of four decentralized STPs is under construction. The said system is also SCADA complaint.
5. State Secretariat building and the Head of the Department building has been completed and being fully operational.
6. Two Residential sectors of Naya Raipur having 2600 and 7500 Housing units has been completed and habitation has started.
7. Two more sectors of Naya Raipur one with the Govt. housing and other with the private housing being done by private developer are under construction.
8. BRTS project under the World Bank scheme is under construction; which is likely to be commissioned in June 2015. The project is with ITES with real time tracking and Passenger Information System (PIS), for which order for 40 AC buses has been placed by NRDA.
9. Lake conservation for 3 Major lakes is underway.
10. Central Park having 58 Hectares is near completion which is having various facilities.